August 2007 Monthly Update
The end of August marked the end of 10 months of fieldwork for
the Joint Courts Archaeological Project. During our tenth month,
our focus shifted away from the delineation of the former limits
of the National Cemetery, which we had largely accomplished by
the end of July, and onto the intensive excavation of previously
discovered graves. Our exploratory excavations in August were
limited to selected areas of the former cemetery that we had
left unexplored due to underground utility concerns or other
accessibility issues. A few small areas of the cemetery within
our overall project boundary remain unexplored, but it is unlikely
that any surprises await us in those areas. We now expect the
total number of individual burials in the project area to be
somewhat greater than 1,100. By the end of August, we had identified
965 graves in the project area; we have now fully excavated 551
individual burials.
August brought us a minor surprise that slightly increased our
scope of work and also provided a useful addition to our understanding
of the history of the cemetery. Early in the month, we learned
that Chicanos Por La Causa (CPLC), the nonprofit organization
that owns and occupies the former bank building at 200 North
Stone Avenue, was upgrading the electrical service to its building
to accommodate a new HVAC system. The upgraded electrical service
will require an external transformer that CPLC plans to install
in the parking lot immediately north of the building. Pima County
has been in regular contact with CPLC since the start of the
Joint Courts project because of the proximity of the CPLC building
to the project area, and both the county and CPLC have long been
aware that much of the CPLC parking lot falls directly within
the limits of the military portion of the National Cemetery.
Thus, when CPLC determined that it would need to disturb part
of its parking lot in order to install the transformer, they
consulted with the county about the potential impact to archaeological
features. The county was already in discussions with CPLC about
temporarily closing the alley on the east side of its building
to allow us to excavate that portion of the cemetery (the alley
will be used as a utility corridor for the future Joint Courts
Complex). As part of the agreement that would give us access
to the alley, and allow us to fully excavate any burials that
lie partially on CPLC property and partly on county property,
the county consented to include the footprint of the proposed
CPLC transformer in the archaeological scope of work. Thus, the
county will have the access it needs to conduct required archaeological
excavations, and CPLC is assured that installation of its new
transformer won’t impact the part of the cemetery under
its parking lot.
The portion of the CPLC parking lot that we explored archaeologically
consisted of a small rectangular area measuring about 20 by 50
feet, which included both the proposed footprint of the transformer
pad and the path of the buried cables that will connect the transformer
to an existing electrical vault in the alley. In this small window,
we discovered four grave pits. Two were located in the parking
lot proper and two were in the adjacent portion of the alley.
The two graves in the alley confirmed that a partial fourth row
of military graves extends north up the alley from Alameda Street.
We had previously identified the three easternmost rows of military
graves in our excavations immediately east of the alley, within
our original project area boundary. Based on documentary sources,
we suspected that a partial fourth row was also present, but
we had not had the opportunity to explore the alley in the immediate
vicinity of the CPLC building. Our recent work in the alley just
north of the CPLC parking lot indicated that the fourth row,
if it was present at all, did not extend north into our original
project area. Like most of the graves we have excavated in the
military cemetery’s three easternmost rows, the burials
in these two graves were previously exhumed, presumably as part
of the U.S. Army’s effort in 1884 to move all of the soldiers
buried in the cemetery to a new cemetery at Fort Lowell, 7 miles
east of downtown.
Of the two graves in the CPLC parking lot, one had been previously
exhumed and one was still intact. We do not know when the first
burial was exhumed, but it was clearly prior to the initial development
of the cemetery as a residential area in the 1890s. We also do
not yet know whether these two burials were of soldiers or civilians;
the archaeological evidence in this regard is inconclusive. We
do know that the military cemetery was occasionally used for
civilian burials (usually because the deceased had some connection
with the army), but we do not know how the civilian burials were
distributed in the cemetery.
Thanks to the removal of an electrical line that served a nearby
traffic signal, we were finally able to remove the sidewalk along
Stone Avenue south of Council Street. Our search for archaeological
features in this area showed that much of it had been badly disturbed
as part of the basement excavation for the former Tucson Newspapers
building. Photographs of the ongoing excavation in 1953 had suggested
to us that the basement excavation extended only to the east
edge of the Stone Avenue sidewalk, but our mechanical stripping
has revealed that the final limit of the 1953 basement excavation
came within 3 or 4 feet of the curb. On the other hand, the southern
half of the basement excavation, which corresponds to the original
1940 portion of the Tucson Newspapers building, did not extend
quite so far west, leaving a more substantial undisturbed strip
under the sidewalk. We have not yet found any grave pits under
the sidewalk south of Council Street, but we have found another
prehistoric pit house, the second in the project area. Like the
pit house found earlier in the central portion of the project
area, this one is well preserved and probably associated with
the Cienega phase of the Late Archaic period (ca. 800 BC–AD
200). Only half of the pit house falls within the project area;
the other half extends under Stone Avenue, just a few inches
below the modern pavement.
Also in August, we were allowed to remove a small section of
the concrete that covers the deeply buried electrical lines still
in place along the south edge of Council Street. The lines will
be removed later this year, but we were eager to know the extent
of disturbance along this corridor, since it will be an important
factor in our estimate of the total number of graves in the project
area. We discovered that the trench for the electrical lines
is about 4 feet wide and perhaps 10 feet deep, or a little less
than half the width of the concrete cap that runs along Council
Street. Much of the remainder of this corridor is also disturbed
by deep excavation for the Tucson Newspapers building. This means
that the number of intact graves likely to be found under the
concrete cap, which runs the full block of Council Street from
Stone to Grossetta Avenue, will be less than we had anticipated.
One other discovery in August is worth noting. Among the features
found under the Stone Avenue sidewalk north of Council Street
was an exceptionally deep grave pit. The depths of the grave
pits found previously in the project area have varied greatly,
but few had exceeded 5 feet, and the very deepest was still less
than 6 feet deep. This grave pit was a full 8 feet in depth,
which makes it a complete exception in the project area so far.
It was so deep and relatively small that it must have been difficult
for the original grave diggers to excavate, since there would
have been very little room for a person to use a shovel. The
grave did not have any other characteristics that would suggest
why it was made so unusually deep.
|