May 2007 Monthly Update
During May 2007, Statistical Research, Inc. (SRI) continued
to make steady progress in its archaeological investigation of
the Joint Courts Complex (JCC) project area. The focus of work
for the month was once again the civilian portion of the National
Cemetery, where we have continued to discover and excavate the
many graves left in place when the cemetery closed in 1875. During
May, the total number of graves discovered in the project area
increased from 359 to 496, for a month’s total of 137 newly
discovered graves. This is the largest monthly increase we have
seen since the project began six months ago and reflects our
work in areas that probably once fell in the oldest and most
heavily used portion of the civilian cemetery. We continued to
excavate in the former parking lot located just north of Council
Street and just east of the building at 240 North Stone, and
we began excavations directly within Council Street immediately
east of Stone Avenue. Both areas have shown a significantly higher
density of graves than we have found in any other part of the
project area, which supports our early hunch that the area below
240 North Stone is also of high density.
The building at 240 North Stone, originally erected as two separate
buildings around 1929, was demolished during May, with the exception
of the concrete slab on which it stood. The careful removal of
the slab itself has begun, and we hope to begin excavation below
the slab in early June. With areas of high grave density to its
south and east, it is curious that immediately north of the building
we have found only a limited number of graves, distributed mostly
in small clusters. This might seem to suggest that the density
of graves under the building gradually diminishes with distance
from Council Street, but just east of the building we found a
sharp break between the old parking lot, where grave density
is high, and the area immediately to the north, which completely
lacks graves. Apparently, the property line marked by the north
edge of 240 North Stone and the parking lot—a line first
established by a city surveyor in 1889 and still in use until
just recently—corresponded with a boundary observed during
the period the cemetery was open. Our historical research did
not find any documentary evidence of such a boundary, but we
hope that its significance becomes apparent as we excavate below
the 240 North Stone slab.
The graves discovered and excavated in May have not varied in
character from the general pattern observed in earlier months,
apart from their generally higher density. All of the graves
were placed with their long axis oriented east-west, with one
exception: a single grave has now been found with a north-south
orientation, though it lacked any other distinguishing characteristic.
The depths of the grave pits continue to vary widely, from only
a foot or so below the modern pavement to as deep as 5 feet.
Most of the graves are found in fairly regular north-south rows,
with occasional irregularities in spacing that suggest deliberate
clusters of graves. Artifacts found in the graves are limited
in number and variety, in large part a reflection of the economic
circumstances of pre-railroad Tucson, where commercially manufactured
goods were expensive because everything had to be brought by
wagon over long distances. In most graves we find traces of wood
from simple coffins, but we rarely find coffin hardware other
than badly rusted coffin nails. Personal items preserved in the
graves are generally limited to the buttons of the clothing worn
by the deceased.
In addition to grave excavation, we have also continued to discover
and excavate post-cemetery features associated with the early
residential and later commercial development of the project area.
The excavation of deep privy pits found in the southern and central
portions of the project area continued, with two pits now exceeding
10 feet in depth. The excavation of these two features has halted
temporarily until we have an opportunity to mechanically excavate
a large area around each pit to comply with OSHA excavation safety
standards, which limit the height of unshored excavation walls.
We have also discovered what is probably another privy pit in
the northern portion of the project area, in the former backyard
of John and Dolores Brown, whose house foundations, dating to
1890, we excavated earlier this year. The excavation of this
pit and other recently discovered residential features will take
place in the coming months.
|