March 2008 Monthly Update
Statistical Research, Inc., carried out its last regular day
of fieldwork for the Joint Courts Archaeological Project on Friday,
March 14, 2008. Sixteen months after we began, we finally completed
excavations in the project area—with the exception of a
narrow utility corridor that remains in service, as discussed
below. We spent the last two weeks of March shutting down the
field operation, backfilling some of the excavations, removing
and servicing field equipment, and cleaning up the site. Our
attention now shifts to the careful analysis of our discoveries,
including the skeletal remains and burial-associated artifacts
from the many graves of the National Cemetery, the staggering
number of artifacts from the many post-cemetery features in the
project area, and the relatively few but important artifacts
found in association with two prehistoric pit houses.
The last two weeks of regular fieldwork were spent on a variety
of excavation tasks aimed at making sure every part of the former
cemetery had been thoroughly explored. An especially important
task was to revisit parts of the project area with the backhoe,
mechanically stripping areas where we had already hand-excavated
all of the graves identified in our original stripping. In parts
of the former cemetery, most notably the area of high grave density
discovered in the western portion of Council Street, the combined
presence of multiple, overlapping graves and a variety of later,
intrusive features (especially utility trenches) made it difficult
to be absolutely certain that every grave feature had been identified
and excavated. Using the backhoe to remove the fill from intrusive
features and then explore beneath them, we eliminated any doubt
about the thoroughness of our efforts. During the first two weeks
of March, we identified another five graves, which we then excavated
by hand.
The total number of graves discovered and excavated in the National
Cemetery now stands at 1,095; the total number of excavated burials
is 1,012. It is possible that these numbers will increase slightly
when we return to the field later this year to excavate below
the high-voltage electrical lines still in place (and energized)
in the project area. A reroute of these lines is currently under
construction in Stone Avenue and Alameda Street, on the west
and south sides of the project area, but the reroute will probably
not be complete until summer. The trench that holds the energized
lines is fairly deep, but the possibility exists that graves
(disturbed or undisturbed) are still present below the trench.
Our fieldwork will not be definitively complete until we excavate
below the trench.
This is the last regular monthly report for the Joint Courts
Archaeological Project. We anticipate providing less-frequent
reports about our progress in the analysis and writing stages
of the project, but we have not yet settled on a schedule or
a format. |