October 2007 Monthly Update
We began excavations for the Joint Courts Archaeological Project
on November 6, 2006, which means the end of October has marked
the end of nearly a full year of fieldwork. From the beginning
of the project, our primary focus has been the excavation of
graves in the former National Cemetery, and we have settled into
a routine that will likely continue with few changes until the
anticipated end of fieldwork on March 14, 2008. By the end of
October, we had identified 1,016 graves in the project area and
had fully excavated 774 of them. We continue to anticipate that,
by the end of fieldwork, we will have found and fully excavated
somewhat more than 1,100 graves. This means that over the remaining
four and half months, or about 18 working weeks, we need to excavate
approximately 350 graves, along with a fair number of historical-period
features that postdate the National Cemetery, including privy
pits, trash pits, and assorted remnants of residential and commercial
architecture.
It was a long time coming, but the reopening of the Stone Avenue
sidewalk along the west side of the project area is finally about
to happen. Once that sidewalk is reopened and our western project
fence is reestablished along its earlier alignment, we will be
closing the sidewalk along Alameda Street at the southern end
of the project area. Construction of the Joint Courts Complex
will involve disturbance and eventual replacement of that sidewalk,
too, which prompted our concern that historic features might
be affected. Our understanding of the limits of the former cemetery
suggest that we will not find many graves here, but we did find
a few graves just north of the sidewalk, within the current project
area. Because none of the assumed boundaries of the cemetery
is neatly defined, it is always possible that a grave or other
significant feature associated with the cemetery may lie under
the sidewalk.
At the same time that we close the Alameda sidewalk, we will
also close the short section of alley that runs immediately east
of the Chicanos Por La Causa building at 200 North Stone. This
alley, which will also be impacted by construction of the Joint
Courts Complex, holds part of the fourth row of graves in the
former military section of the National Cemetery. Based on the
results of our excavations in the other three rows earlier in
the project, most of the burials in the fourth row were likely
exhumed in 1884, after the U.S. Army was asked by the City of
Tucson to stop using the cemetery. The graves have undoubtedly
also been disturbed by the many utility lines placed in the alley
over the intervening years. Despite these disturbances, it is
important that we document and recover what remains of these
features before the construction project begins.
The end of October saw us returning to three tasks that will
occupy us for most of the rest of fieldwork. First, we have begun
mechanical stripping of the previously unexplored areas outside
the presumed limits of the former cemetery, areas we had mostly
disregarded during our focus on determining the limits of the
cemetery and the total number of graves. These areas, which lie
north and east of the cemetery, hold a variety of architectural
features from the commercial development of the project area
that began in the 1920s, including extensive cement slabs, heavy
concrete footers, and industrial features such as automobile
hoists. As we remove the upper layers of commercial features
(with the assistance of our demolition contractor), we occasionally
find less substantial remnants of earlier residential architecture,
including foundation fragments and construction debris.
Second, we are now returning to the excavation of previously
discovered privy features in the project area, which we had put
on hold as we devoted our equipment and crews to grave excavation.
The area around two very deep, partially excavated privies in
the southern portion of the project area is now being mechanically
terraced to comply with OSHA excavation safety standards. Once
the terracing is complete, we will assign crews to finish the
documentation of these important features. The excavation of
at least one other privy, found in the central portion of the
project area, is also being resumed. And in our ongoing stripping
of the areas outside the cemetery we may still discover other
privies or other trash-filled features that will require excavation.
Third, we are just now returning to the excavation of graves
in Council Street, where earlier this year we discovered the
very dense concentration of graves mentioned in previous monthly
reports. We excavated about half of the dense area before the
monsoon season began, then decided that it was best to postpone
further excavation until the threat of heavy rains was over.
Now that we are back into the street, we are once again involved
in a much more complicated kind of excavation than most of the
rest of the cemetery has required, with crowded, overlapping
graves and multiple, crosscutting utility trenches. |